AutoQuiz: How to Create a Bill of Materials for a Project Purchase

The post AutoQuiz: How to Create a Bill of Materials for a Project Purchase first appeared on the ISA Interchange blog site.

AutoQuiz is edited by Joel Don, ISA’s social media community manager.

Today’s automation industry quiz question comes from the ISA Certified Automation Professional certification program. ISA CAP certification provides a non-biased, third-party, objective assessment and confirmation of an automation professional’s skills. The CAP exam is focused on direction, definition, design, development/application, deployment, documentation, and support of systems, software, and equipment used in control systems, manufacturing information systems, systems integration, and operational consulting. Click this link for information about the CAP program. The following question comes from the CAP study guide, Performance Domain V, Deployment.

autoquiz-20170106-bill-of-materials-project-purchase

A bill of materials for purchase of cable on a project is created by completing a material:  

a) procurement
b) inspection
c) take off
d) requisition
e) none of the above

   

<span class="collapseomatic " id="id2278" tabindex="0" title="Click Here to Reveal the Answer” >Click Here to Reveal the Answer

A material takeoff is the process of analyzing the drawings and determining all the materials required to accomplish the design. We then use the material takeoff to create a bill of materials. Inspection does not aid in creating a bill of material. Procurement and requisition are activities that occur after the bill of materials is complete.

The correct answer is C.

Reference: Whitt, Successful Instrument and Control System Design.

 

 

 

Source: ISA News